Ti-Phoenix
A 289,365 SF cold storage facility developed in El Mirage, Arizona. Sterling provided the foundations, office slabs, concrete pavement, sidewalks & curbs.
- Schedule: January, 2023 to August, 2023 
- Project total yardage: 6,900 Yards 
- Slab work: (8,432 SF) of office slabs, (5,938 SF) of slab-on-decks & (3,708 SF) of dock pit slabs. 
- Foundations work: (241) columns, (204) CIP piers, (4,708 LF) continuous footings & (2,606 LF) CIP walls. 
- Exterior work: (183,560 SF) of concrete pavement, (7,770 SF) sidewalk & (5,944 LF) curb & gutter. 
 
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
             
              
              
            