MEC

A 44,210 SF tilt-up warehouse developed in Tecumseh, Michigan. Sterling provided the foundations, slabs, tilt-up panels, concrete pavement & sidewalks.

  • Schedule: November, 2021 to April, 2022

  • Project total yardage: 4,850 Yards

  • Slab work: (44,210 SF) of warehouse slabs.

  • Tilt Panel work: (25,055 SF) of tilt panels.

  • Foundations work: (47) columns, (2,603 LF) continuous footings & (1,273 LF) CIP walls.

  • Exterior work: (134,314 SF) of concrete pavement, (1,529 SF) of combined sidewalks & (2,817 LF) of curb.