SHAH - 200
A 208,350 SF tilt-up warehouse developed in South Bend, Indiana. Sterling provided the foundations, slabs, tilt-up panels, concrete pavement & sidewalks.
Schedule: October, 2022 to May, 2023
Project total yardage: 9,500 Yards
Slab work: (208,350 SF) of warehouse slabs, (5,616 SF) of slab-on-decks & (8) dock pits.
Tilt Panel work: (67,000 SF) of tilt panels.
Foundations work: (83) columns, (2,352 LF) continuous footings & (67 LF) CIP walls.
Exterior work: (175,000 SF) of concrete pavement & (750 SF) of combined sidewalks.